Seward US-83 (South)
Passing lanes, overlay, and patching on US-83 in KS.

Scope of Work
J&R added passing lanes, milled and overlaid the existing lanes, and patched PCCP sections across 13.8 miles of US-83 running north from the Oklahoma state line through Seward County, Kansas. Crews placed 133,646 tons of asphalt on a $20.3 million contract.
The project ran from March 2022 through October 2023, covering two construction seasons. At over 133,000 tons placed, this was the largest job in J&R's recent project group by tonnage.
The scope combined three different types of work under two KDOT project numbers, KA 2220-01 and KA 5600-01, into one contract: passing lane additions, mill-and-overlay on existing lanes, and PCCP patching where the underlying concrete pavement required repair before the new asphalt surface course could be laid down across the full corridor.
Tonnage
133,646 tons
Location
Seward County, KS
Timeline
20 Months